3 out of 4 – On the home stretch
Friday I finished framing and sheathing the upper south roof which now leaves only the last upper north roof to complete. The process is going faster now that I am…
Foundation Rebar Primer
…all of the horizontal bar had already been placed. While waiting for the reply to come the following morning, I tossed and turned all night worrying I was going to…
We have Asbestos!
…but the drywall and utility floor do. I will call actesenvironmental.com to come in and remediate. I am allowed to do this myself as long as no other person would…
Finally!
…felt like a milestone for 2019, to complete the majority of the unfinished window returns from last year and complete the final staining of the south, north elevations and second…
All Decked Out
…complete the system. Gable Wall – Step 1 Identify where ceiling plane is located on truss chords/studs and seal plywood to truss components along this line (can just see red…
Milestones
I am pleased to say it has been a busy and successful last two weeks with many important milestones being completed. I met with Cascadia Windows & Doors on the…
Hangers, Humps, and Roadside Bumps
…I was told that there are no ‘barbs’ (what I had first called them), and that there nails were just repackaged ‘common’ nails. See common nail on left and official…
The B.A.T. – She Flies Once Again!
…1.0 met its demise on December 11. 2014 during a strong wind storm. While the installation of the new tarp is just about complete, there was some drama. I started…
A poor pour! – But it is complete.
…placer commented, if a day finishes with the task complete and mistakes rectified, then no harm no foul. The End Result looks great. Tomorrow will be a much needed day…
I’m Floored!
…sheets today! Since your last visit the following tasks were completed: finished framing the basement bearing walls (Ted came by one day and helped with the majority of the East…